Thursday, June 18, 2015

Polish LNG: terminal in Swinoujscie made 50 thousand. Inspection … – Onet.pl

length of the pipelines in the terminal area is 47 kilometers – roughly as much as the distance from the ground to the mesosphere. The length of electrical cables is 470 km, and corresponds to the distance in a straight line from Gdansk to Krakow. As part of the load to check it is still 1536 and 5718 line pipe measuring points. Added to this is complex technology that only makes its debut in Poland.

“In order to dominate over such a complex undertaking , installation is divided into about 650 sub-systems, which are run in strict sequence. In total, commissioning of the LNG terminal requires the coordination of more than 6,000 different processes and take into account all the necessary safety requirements and quality control “- says Maciej Mazur, director of the Office of Corporate Communications Polish LNG.

He added that the supervision over the quality consists of several levels: the first is quality control services contractors, then service general contractor (GRI) and the Transport Technical Supervision (TDT), which aims at the construction site of a permanent representation. Checks known. investment supervision (NI) holds a Norwegian company Multiconsult Group, and certification of certain plant belongs to the so-called. Notified Body (TÜV Nord Hamburg).

According to experts, the quality control system in gazoporcie is extensive and meticulous based on global standards.

“The LNG terminal is a mega industry in the nomenclature of the investment. The investment will affect the environment economic and social Polish. With this technology, the issues of safety and quality for the company’s installation are Polish LNG, as for every investor a similar project priority “- told PAP Robert Zajdler of the Sobieski Institute.

Every day at the construction site work is supervised and controlled by inspectors TDT and TUV. In addition to inspections surveillance units, all phases of the works are controlled and confirmed by inspectors and specialists Investor Supervision of individual industries. Inspectors TDT They perform up to 20 loads per day, as specialists TUV. Inspections are carried out not only on construction sites, but also suppliers’ factories.

“Control is really very much and take place at every stage of the project. , Control is exercised not only state institutions but also external, “- says Mariusz Ruszel from the Department of Economics Department of Management Rzeszów University of Technology, a specialist in the gas market and energy security.

Polish LNG ensures that the quality control system of the LNG terminal in Swinoujscie has already passed nearly 240 thousand. detailed reports. This is 94 per cent. of all documents that are required by the so-called. Detailed Quality Control Plan . For each such report may fall even several protocols reception.

The LNG terminal in Swinoujscie is one of the largest Polish energy investments in recent years, as recognized by the Polish government as a strategic energy security of the country. The investment will enable reception of natural gas by sea from virtually any direction in the world. By accessing the global LNG market, Poland strengthen its security by diversifying supply of raw material.

The initial regasification capacity will be 5 billion cubic meters. per annum and will correspond to one-third of Polish demand for natural gas. Ongoing feasibility study for the expansion of terminal capacity by half – to 7.5 billion cubic meters. Progress of the development at the end of May. It amounted to 97.5 per cent. This year, according to assurances Polish LNG terminal arrives first delivery of liquefied natural gas.

LikeTweet

No comments:

Post a Comment