Mine Makoszowy sold coal at 129 million rubles, and 138 million rubles received from the budget – Onet.pl

According to the company, closed the mine produced this year good. 664 thousand. tons of coal, of which it sold about. 662 thousand tons, and nearly 2 thousand tons are reserves.

mine Makoszowy the company was in restrukturyzacyjnej in the spring of 2015. pursuant to an agreement of 17 December of last year, the agreement of the miners ‘ unions with the government, ewa kopacz. The agreement provides, in particular, in the case niepozyskania investor to mine her crew has a guaranteed job in the other mines. The September auction for the sale of the plant failed.

Until now, the Declaration and move to other mines went well. 950 of less than 1350 employees. OK. 320 people must remain in the factory and work at its elimination. In accordance with the plan, until the end of this year will include the distribution of 362 people, of which 163 have already begun work in other mines belonging to the Polish mining Group (PGG) and mine-Boars in Jastrzębskiej Company Carbon steel.

As reported on Wednesday, REUTERS representative PGG Thomas Głogowski, the Group has adopted early for work 58 miners from the mine Makoszowy. They work in different parts of the mine Ore (Bielszowice, Halemba, Number), and the shaft Boleslaw the Brave, where the first two miners was made shortly before Christmas.

the Following methods miners from Makoszów to PGG will be implemented in the following days. “Including compliance with employment reported by 447 employees of the mine Makoszowy, including approx. 150 with the surface,” said Głogowski.

Although technically the last day of coal mining in Zabrze will be the nearest Friday, in fact, technical considerations made the decision that now manufacture is at a minimum. When fully suspended, will begin the dismantling of underground devices and machines, and preparation for liquidation of mine workings. The schedule and projected cost of these works prepared the plan of liquidation. Its approval of the resort energy needs to happen before the end of January.

According to earlier information, in accordance with the decision of the European Commission on the notification of the Polish program pomocowego for mining, mine Makoszowy only until the end of the current year can take advantage of budget subsidies for production losses that hastened the decision to end coal mining.

Makoszowy is the last operating mine in that mountain-Zabrze. Its origins date back to 1890, when the excavation works are carried out under ground, to the West of the mine Guido (today is mine old, one of the biggest attractions the Trail of technological Monuments-Anything. Province) is diagnosed backup field of the mining industry. In 1900 there began the construction of mines, originally designed for other zabrzańskiej mine. Soon, however, there are Makoszowy became independent of the mine, where mining began in the spring of 1906; in the spring of this year the plant celebrated its 110 anniversary.

In August 1958. mine Makoszowy occurred one of the greatest tragedies in Polish mining industry – a shooting at 300 meters under the ground were killed 72 miners, 87 seriously, literally would tear burning. In the 60-ies. last century the mine was completed. A record production was reached in 1988, when it produced more than 5 million tons of coal, with employment of about 10 thousand. people. Starting in 1993. Makoszowy belonged to Gliwice Company Carbon steel, and since 2003. in the Coal Company. July 1, 2005. the mine combined with gliwicką Sośnicą to 10 years from now again divide both bets. Last spring Makoszowy to be in the Company of the restructuring of Mines, where was the only mine still wydobywającą coal.

About keeping mine fought Union members with Makoszów, urging that she might rentownie to work and to attract investors. Representatives of SRK showed, however, that the mine makes a loss, and the potential investor should pay the entire rate of awarded state aid. For the September tender was one subject which, however, did not fulfill the required conditions.

(sp)