the electricity of high voltage transmission station by typing in the design of an energy bridge between Poland and Lithuania, opened on Thursday near Siedlce Deputy Prime Minister Janusz Piechociński.
The substation 400kV / 110 kV Siedlce Ujrzanów is part of a 400 kV power line Miłosna – Siedlce Ujrzanów, part of the cross-border merger between the Polish and Lithuania.
This is the third after SE and SE Lomza Oltarzew station, built in the strategic Polish-Lithuanian power bridge.
In contrast, measuring 89 km 400 kV transmission line connecting Miłosna of Siedlce, is the second investment made in Line the project. The section passes through 3 counties and 12 municipalities Mazowieckie voivodship.
Most Energy aims to connect the European energy market and of the nine Baltic Sea countries, including Lithuania, Latvia and Estonia. The project aims to contribute to the strengthening of energy security of Polish and Europe.
Power ring around the capital
Deputy Piechociński during the opening ceremony stressed that the project confirms the Community thinking in the European Union and is part of the building energy union. In addition – he reminded – helps close the energy ring around Warsaw.
He expressed satisfaction with the implementation of the projects principally in energy union such as – support in times of trial, synchronization and coordination of energy systems, increased energy efficiency of .
– In the years 2010-2015, we published and we will release only in networks of high voltage 4.5 billion zł. The term, which is before us, by 2020 we will spend 7.5 billion – said Piechociński.
He also recalled that since 2010 only in Poland, built more than 600 km of new high-voltage lines , modernized twice as much, on networks of high voltage transformers installed hundreds of the latest generation. He pointed out that in the implementation of major energy projects involved are not only Polish company, but Poland modern technology electrical and electromechanical industry.
At the opening of another section of the Polish-Lithuanian energy bridge was also attended by a representative of the Directorate General of the European Commission. Wolfgang Munch energy. He emphasized that the transmission infrastructure built by Poland and Lithuania is an investment strategy, serving the security and sustainability of energy supply and competitiveness of the EU market.
The total cost of construction of an energy bridge between Poland and Lithuania are valued at 1.8 billion zlotys. Nearly 870 million zł came from EU funds. The project on the Polish side of the Polish Power Grid execute.
High Voltage with residents
The President reminded the PSE Henryk Majchrzak, as part of a bridge between Poland and Lithuania have already completed more than half of the investments. Closing of the investment is planned for the fourth quarter of 2015 years. President of the PES assured that it will be completed on time. He added that the project remained to close the connection Lomza – Elk with an electricity station in Stanislav and the combination of Elk – border with Lithuania.
As pointed out by the PSE, built in Ujrzanowie 400/110 kV substation is also important for Siedlce. It is the only facility of its kind in the area of the city, which allows you to transform the voltage of 400 kV up to 110 kV. The station is also ready to bring in the future new ground lines.
The property is unattended, remotely controlled and monitored from national and regional dispatching centers.
Majchrzak President also talked about further plans to build a line 400 kV transmission, among others domykających Electricity ring around Warsaw. He said that section Kozienice – Siedlce Ujrzanów is implemented according to plan and he predicts that it will be ready for the end of 2017.
Instead, there are problems with the implementation of the Kozienice – Oltarzew – he said. Against the construction of high-voltage lines protesting residents of the western suburbs of the capital.
– Those sites are actually a lot harder. They are mostly residential areas, we know that this is a bedroom of Warsaw. From the beginning, we are aware of these difficulties, because we very involved dialogue with residents – said the head of PSE. As he explained, was able to convince people that your investment is needed, but the social side wants to influence the course of the line.
– About how much will a balance between the interests of all parties, it would certainly use these tips and this project also will process – he stressed.
Specustawą for strategic projects
In the implementation of strategic power projects can help the so-called. Specustawa on transmission corridors. – These are some solutions that will allow us to keep moving forever – he noted. With specustawie – explained – will be possible. Close within a specific deadline proceedings concerning the determination of ownership.
Over the draft law on the preparation and implementation of strategic investments in transmission networks is currently the Sejm. During the next session, MPs will consider amendments tabled during the second reading.
Majchrzak added that in case of a non-strategic investments, there is only a problem of rising costs. – In the case of investment strategy may result in serious complications, because, for example. Line from Kozienice to Oltarzew is the key to exit (from the power plant Kozienice – PAP) capacity 1000 MW with a value of 5-6 billion zł – said the president of PSE.
PAP