Gaz-System plans expenditures approx. 1-1.1 billion zł per year on infrastructure – Money.pl

Gaz-System assumes capital expenditures of approx. 1-1.1 billion zł per year over the lifetime of the strategy for 2025., CEO Tomasz Stepien. The company will focus on expanding the transmission infrastructure, is considering two possible variants in its northern part.

“We want to maintain the level of investment per year as it had been in good years, that is 1-1.1 billion zł” – Stepien said during a press conference.

He added that the investments will be financed from its own funds and the EU, where the funds are to come from the transfer fee. He stressed that the company does not intend this fee raise.

“We want to make those investments that have already ended and build a backbone transmission network, which will be able to bring gas from various directions for the economy” – said the president.

the Company, together with the Danish operator Energinet.dk analyzes the possibility of building the Baltic Pipe connecting Poland and Norway. The combination would provide the ability to transfer 10 m3 of gas per year. As part of the basic variant it is analyzed the development of the LNG terminal regasification capacity of about 7.5-10 billion m3 and expansion of the transmission system in north-west. In this variant, it is possible to build an underground gas storage facility in Damasławku.

As part of the alternative variant Gaz-System takes into account the construction of a floating regasification terminal (FSRU) in the region of the Gulf of Gdansk (up to 10 billion m3 of gas), and developing the transmission system in the south-east and the construction of an underground gas storage facility in Bialogard Pomerania.

President pointed out that decisions concerning the selection option should be taken within the next year or sooner. Then it will be updated 10-year development plan.

“In less than a year, we expect the results of the feasibility study. We’ll wait a few more months to decide,” – he said.

In addition, work is underway on the construction of gas connections with Ukraine and Lithuania, which should be completed in the years 2019-20.

“We have the full support of the President of the Energy Regulatory Office, we are after a few conversations” – Stepien stressed.

last week, the board of directors of Gaz-System board approved an updated strategy for the company by 2025. the main strategic directions are:

– building a strong position of the company through active involvement in the process integration of the European gas market, primarily through the construction of infrastructure,

– ensuring the safety of the transmission system and the continuity of transmission services.

– improving operational efficiency and organization of the company.

the investments are designed to allow the development of an integrated regional market with a capacity of approx. 70 billion m3 / year.

gas Transmission operator Gaz-System is a strategic company for the Polish economy, responsible for the transmission of natural gas and the management of major pipelines in Poland.